As-Built Drawings for DOB Sign-Off in NYC: When the Job Does Not Match the Plans
If you need as-built drawings for DOB sign-off in New York City, the reason is usually simple. Construction wraps up, the work looks good, and the drawings on file no longer describe it. A door moved eight inches. Someone reversed a door swing so it would clear a radiator. The kitchen island shifted, and the appliance layout changed with it. None of that felt significant on site. All of it matters when someone has to certify that the work matches the approved set.

As-Built Drawings for DOB Sign-Off: Why the Finished Job Never Matches the Approved Set
Construction is a negotiation with reality. A riser turns up where the drawing showed clear wall. A beam sits two inches lower than expected. The owner sees the framed opening and asks for the door to swing the other way. Each decision is reasonable on its own, and each one happens in an afternoon without anybody redrawing anything.
By the end of the job, dozens of those small decisions have accumulated. The contractor knows what the crew actually built. Their architect knows roughly. The filed drawings, however, still show the design from eighteen months ago. That gap is the problem, and it surfaces at exactly the wrong moment.
What the Building Code actually says
Two sections control this, and both are worth reading before you schedule anything.
First, NYC Administrative Code § 28-104.3 covers amended construction documents. It requires the design professional to file and clear amendments before the work finishes. Then it opens a narrow door:
The department may allow minor revisions of construction documents to be made and submitted to the department after the completion of work but prior to sign-off of the work.
That sentence is the whole reason this service exists. For minor revisions, the code expects you to document reality after the fact but before closeout. For anything beyond minor, the amendment was legally required before the work happened, so the filing becomes corrective rather than routine.
Second, § 28-116.2.4.2 governs the final inspection before a Letter of Completion. The report must confirm that the work is “in substantial compliance with the approved construction documents.” This is the part people underestimate. Sign-off is not a walkthrough that someone passes or fails on vibes. It is a professional attestation. If the drawings do not describe the building, no honest professional can sign that statement, and the job simply stops.

The 2021 Change That Reshaped As-Built Drawings for DOB Sign-Off
For years, a standalone AI-1 form could carry a minor plan change on its own. Plenty of guidance online still says so. That route closed. A DOB service notice effective March 15, 2021 states plainly that all minor plan changes after approval require submission as a Post Approval Amendment.
In practice, that means one thing. If the plans change after approval, you are filing a PAA. Several details matter:
- Only the Applicant of Record can file it, and it must be the same RA or PE who filed originally.
- The filing fee is $100, plus any additional fees if the scope or cost changes.
- Only one PAA can be open at a time on a filing, so every change has to go into that one submission.
- You upload a full plan set as a single PDF, with an AI1 form as the last page describing the changes.
Notably, DOB has never published a checklist defining “minor.” The service notice sets out process, not criteria. The distinction that survives in the code is about timing and consequence, not about whether you file at all.
What We Do On Site to Produce As-Built Drawings for DOB Sign-Off
You send the approved PDF set. We come to the property with it, and we measure what is there.
We dimension walls from fixed points instead of scaling them off the old drawing. Every door and window opening goes on the plan at its true width, and the swings match what the carpenter actually hung. Ceiling heights go in room by room, because bulkheads and dropped soffits rarely land where the design showed them. Plumbing fixtures, appliances and equipment are located. Then we red-line every deviation directly onto your set, so your architect can see at a glance what moved.
Finally, we update the CAD file. You receive layered AutoCAD DWG and PDF reflecting the building as it stands, ready for your RA or PE to file the amendment and request the inspection.

Three changes that are never minor: use, egress and occupancy
Most field deviations are cosmetic in code terms. Three categories are not.
Change the use, the egress or the occupancy, and the job needs a new or amended Certificate of Occupancy. That converts an ordinary Alteration filing, which would have closed with a Letter of Completion, into an Alteration-CO. DOB names the triggers directly for multiple dwellings, including changes to egress width, travel distance or exit locations, structural modifications, added or removed plumbing and gas risers, and anything affecting occupancy load.
This is why a moved partition deserves attention rather than a shrug. A wall that narrows an exit access is not a drafting detail. It can reclassify the entire filing.
The energy paperwork nobody budgets for
Here is the requirement that catches people late. DOB’s required documents for construction sign-off include a TR8 progress inspection report and an EN2 certification of conformance with the as-built energy analysis.
The progress inspector must certify that as-built energy values match the approved energy analysis. If construction changes occurred, your energy professional has to prepare an as-built energy analysis that demonstrates compliance. In other words, a field change to insulation, glazing, lighting or HVAC forces its own as-built documentation, whether or not anyone noticed a wall move.

The clock: one year, then thirty days
Two deadlines are worth writing down, both from 1 RCNY § 101-10.
Where no Certificate of Occupancy is required and an approved agency performs the final inspection, that inspection must happen after all permitted work is complete and no later than one year from the expiration of the last valid permit. The inspection report must then be filed within thirty days of the inspection itself.
Owners often assume closeout can wait indefinitely. It cannot. The window is finite, and it starts running from permit expiration rather than from the day the work finished.
What happens when the job never closes
An open job is quiet until it is expensive. Because DOB requires no open applications before issuing a Certificate of Occupancy, one unclosed Alteration can block an unrelated CO on the same building. Buyers and lenders raise it during diligence. Responsibility follows the property, so a current owner inherits whatever a previous owner left open.
Meanwhile, sign-off is not permanent. A progress inspector can remove certification from a final technical report, which reverts a permit from signed-off back to permit-issued.
How this fits a co-op or condo alteration agreement
Most alteration agreements treat DOB closeout as the end of the project rather than the end of construction. Boards and managing agents commonly want evidence that the job closed before releasing a security deposit. Requirements vary building to building, so read the specific agreement, but the pattern is consistent enough to plan around.
If you are still at the front of a project rather than the end of one, our guide to as-built plans for NYC co-op and condo alteration agreements covers what the board package needs.
Frequently Asked Questions
Do I need as-built drawings for DOB sign-off if only a few things moved?
Probably yes. The final inspection report attests to substantial compliance with the approved documents. If the filed drawings show a door on the wrong wall, that attestation is inaccurate. Small deviations are usually handled as a Post Approval Amendment, which still requires a drawing set showing the built condition.
Can you file the PAA for us?
No. Only the Applicant of Record, a registered architect or professional engineer, can file it, and it must be the same professional who filed the original job. We produce the measured drawings your RA or PE files with.
Do you need to see the approved plans first?
It helps considerably. Send the approved PDF set with the quote request. We mark deviations directly against it, which is faster for your architect than comparing two independent drawings.
How long does the site visit take?
A studio takes about 30 to 60 minutes. Larger apartments and commercial floors take longer. We work across all five boroughs.
What do we receive?
A red-lined copy of your approved set showing every deviation, plus updated layered AutoCAD DWG and PDF drawings of the building as built. See what determines as-built survey cost in NYC for pricing.